Ob'yektning interaktiv rejasi
Beruniy sh. o`ng tomoni.
Urganch sh. chap tomoni.
Urganch sh. chap qirg`og`i, Cholish p.  Sizni qiziqtirayorgan chorak havolasiga bosing (
*
 )
IV chorak * - 188116 m3 PK 7+85 ga trubalarni o`rnatish bilan BTBQ 2,0х2,0 - 1 dona
III chorak  * - 27525 m3 PK 2+94 ga trubalarni o`rnatish bilan BTBQ 2,0х2,0 - 1 dona
II chorak  * - 34359 m3
I chorak * - 23000 m3
PK 11+43 PK 10 PK 9 PK 8 PK 7 PK 6 PK 5 PK 4 PK 3 PK 2 PK 1
Jami Yer ko`tarmasining balandligi 14,54 m
Ko`tarmaning umumiy hajmi 330 320 m3
Jami bajarilgan ishlar hajmi 273 000 m3
1.01.2011 ga qoldiq 57 320 m3
BTBQ trubalari * 2,0 Х 2,0