Interactive plan of the object
Right side of Beruniy city
Left side of Urgench city.
Left bank of Urgench city, Cholish settlement  Press a link of the quarter you are interested in (
*
 )
IV quarter * - 188116 m3 with the installation of pipe on на PK 7+85 EICP 2,0х2,0 - 1 pcs.
III quarter  * - 27525 m3 with the installation of pipe on PK 2+94 EICP 2,0х2,0 - 1 pcs.
II quarter  * - 34359 m3
I quarter * - 23000 m3
PK 11+43 PK 10 PK 9 PK 8 PK 7 PK 6 PK 5 PK 4 PK 3 PK 2 PK 1
Total Road bed hight 14,54 m
Total volume of earthfill 330 320 m3
Total volume of executed works 273 000 m3
Remains for 1.01.2011 57 320 m3
EICP pipes * 2,0 Х 2,0