Cement concrete. Kamchik pass 2013-2014. Cost: 1,100,000 USD - Photo gallery
01. 01. 2014.
«Reconstruction and construction of cement highway with a length 58 km on highway A-373 Tashkent-Osh on the section 116-190 km, passing through Kamchik pass»
Customer:
|
«Corsan Corviam Construccion SA» Ispaniyai "Allianse Capital K / S» Dutch
|
General contract:
|
LTD «ROADMAX» Uzbekistan
|
Chief Project Engineer:
|
JSC "YULLOYHABYURO"
|
Completion date:
|
2014
|
The object is a reconstruction of highway and construction of cement concrete highway with length of 58 km. The task of our company includes submission for concrete unit materials with further supply ready-mixed concrete to paver Wirtgen 1600.
|